Daily game plan and recap for HQ2 electrical work with Start2Finish Contracting.
🎯 Focus: Finish devices room by room, clean and safe
Project: Brady mini mansion (Alexandria, LA)
General Contractor / Owner: Start2Finish Contracting — Diante “Boo Brady” Calvert
Support: Square Bidness Tech Lab on site as part of the Start2Finish team
for layout, counts, and documentation.
What You Knocked Out
Field recap so you don’t need the notebook.
✔ Master Bedroom — all 4 switches replaced
✔ Master Bedroom — old ceiling fan removed, new ceiling light installed
✔ Living Room — 3 ceiling fans finished
✔ Dining Room — 3 plugs replaced
✔ Washroom — 3 plugs replaced
✔ Hallway — 1 plug replaced
This stacks on top of Bedroom 2 work, earlier outlets, and all the other device counts already tracked on the
Start2Finish Progress page.
Still on Deck
Clean list so you know exactly what’s left when you walk in.
▫ Bedroom 2 — closet lights
▫ Hall Bath — 2 switches & 1 outlet
▫ Kitchen — 5 outlets
▫ Full walk-through — catch any missed plugs or switches
Main contract: 30–40 recessed lights still ahead — all of this device work is prep and proof.
Flow for the Next Session
1️⃣ Hit Kitchen outlets first — high use, high visibility.
2️⃣ Knock out Hall Bath (2 switches + 1 outlet) in one pass.
3️⃣ Finish Bedroom 2 closet lights.
4️⃣ Walk the full house once with the tester — verify every device.
You’re not guessing — you’re clearing the board.
Every switch and plug you finish is one less thing in the way of recessed lights and datacenter work.
Square Bidness Tech Lab — Field Discipline