| Master Bedroom |
Devices swapped to new spec, ceiling fan installed and running, plates installed, and dimmer set for the
master lane. Room reads as fully finished and lender-ready.
|
Done |
| Bedroom 2 |
Sockets and switches previously completed; now fully finished with matching plates and clean screw lines.
Ready for photos and future staging.
|
Done |
| Living Room |
All outlets changed, 4-gang switch bank completed, final plate installed, and dimmer set for the living
room lane. Living room lighting now has smooth control and a clean wall presentation.
|
Done |
| Kitchen |
Plugs and switch banks updated, kitchen dome light swapped, and plates installed. GFCI / sink-side
locations verified and tightened during final tester pass.
|
Done |
| Laundry / Washroom |
Devices changed, laundry light swapped, and plates installed. Tester pass completed so outlets read clean
before machines move back in.
|
Done |
| Half Bath (by Kitchen) |
Light switch and plug previously upgraded, hall light by half bath changed, and plates installed. Wet area
now reads as finished from door to mirror.
|
Done |
| Full Bathrooms |
Both full baths now have upgraded lights and matching plates. Master bathroom domes replaced, cans
converted to canless per Brady’s request, with dimmer control tied into the master lane.
|
Done |
| Master Closet |
Dome fixture swapped and plates installed. Closet reads bright and even when doors open — no unfinished
devices.
|
Done |
| Hallways |
Multiple 3-ways and standard switches upgraded, hall light near half bath swapped, and dimmer added in the
selected hall location. Plates installed with screws lined one direction.
|
Done |